October 29, 2026
On the Clara Barton Parkway near Lock 10, one lane is closed from 7 a.m. to 5 p.m. and the speed limit drops to 30 mph through the work zone. Eleven miles upriver, trucks run up and down Pennyfield Lock Road. Between those two points, a contractor is staging at Carderock and the Swains Lock parking lot is fenced off.
Most of this traces back to one event. On January 19, 2026, the Potomac Interceptor failed along the Clara Barton Parkway in Cabin John. This large sewer line runs beside the canal. After the failure, DC Water inspected all 54 miles of the line, using LiDAR to measure wall thickness and sonar to find blockages. That inspection found more sections that needed repair, and several of them sit beside the towpath access points Potomac uses most. As of this week, two of those repair sites are scheduled to stay active into 2027.
Mileposts and statuses below come from the National Park Service's C&O Canal conditions page, last updated October 14, 2026, along with the project pages linked in each section.
| Access point | Milepost | Status in mid-October | Posted end point |
|---|---|---|---|
| Lock 10 | 8.8 | Parking and towpath open; short delays as equipment moves | Pipe work through February 2027 |
| Carderock | 10.5 | Tunnel down to one alternating lane; Parking Lot 1 reduced; restrooms closed, portable toilets on site | None posted |
| Great Falls Tavern | 14.3 | Visitor center, lot, restrooms, overlook and trails open | No work zone listed; boat rides closed for the season |
| Swains Lock | 16.7 | Parking lot closed since October 13 | "Several weeks," no date |
| Pennyfield Lock 22 | 19.6 | Pipe repairs; road delays, limited parking | Construction in December, restoration in January |
| Rileys Lock/Seneca | 22.8 | Seneca Aqueduct and parking open | No work zone listed |
The emergency repair in Cabin John was finished months ago. DC Water says full flow returned to the interceptor on March 14. The work at Lock 10 now is a separate project. It rehabilitates a 2,700-foot section of 72-inch and 66-inch pipe between the I-495 interchange and Lock 10. Crews are sliplining the pipe while bypass pumps carry the flow around the work, and DC Water's project page expects construction to continue through February 2027.
The Park Service is also reviewing a separate proposal to slipline a priority section from Lock 14 down to Lock 10. That plan would run four 30-inch bypass pipes along the Clara Barton Parkway shoulder. The project page places the site outside the park's formal visitor-use areas and gives no end date.
The two agencies describe Lock 10 differently right now. The October 14 NPS conditions page still lists a caution that DC Water is "managing a sanitary sewer overflow" near Lock 10 and says visitors there may notice odors. DC Water says the river itself has recovered. On October 7, it announced that expanded testing at six Maryland locations above and below the overflow site found oxygen, nutrient and metal levels within the river's normal range, with no evidence of lasting harm from the collapse. In a September 23 presentation to the Brookmont Civic League, DC Water said cleanup and restoration in the drainage channel, culvert, tributary and canal were scheduled for this fall.
The inspection's most urgent finding upriver was at Muddy Branch near Pennyfield Lock. This section of the interceptor carries about six million gallons of wastewater on a typical dry day, and it sits upstream of drinking water intakes on the Potomac. The job covers about 1,700 feet of 60-inch pipe.
The schedule has moved twice. When work began in June, WTOP reported that repairs were expected to last through the end of September. The first phase finished on July 27, when crews lined the most damaged 175-foot section, which is encased in concrete, with geopolymer. Sliplining the rest was supposed to start in late August. At an October 7 meeting with the Tobytown community, DC Water explained that saturated silty soil and groundwater had slowed the work. The new plan is grouting, dewatering and a WSSC lateral bypass in October, permanent sliplining in November, construction through December, and substantial completion in January 2027. The Pennyfield project page says the same thing in shorter form, with construction expected to finish in December and site restoration in January if weather and conditions cooperate.
What that means at the lock:
Two other projects add to the pipe work, and neither is connected to the interceptor.
At Swains Lock, the Park Service is still repairing damage from a flood on July 8, 2019. The work replaces a damaged timber retaining wall at the parking area with a fill-and-topsoil embankment and repairs the shoulder, drainage, rockery and streambed. The lot closed on October 13 for "several weeks," and the NPS project page, updated October 15, gives no reopening date. Lockhouse 21 is still accessible, and NPS points visitors to the Great Falls and Pennyfield lots for towpath parking. Since Pennyfield has limited space of its own this fall, Great Falls is the most practical of those two options. The Swains hiker-biker campground is open.
At Carderock, an alternating one-lane closure at the tunnel began July 27. The NPS tunnel repair page originally scheduled the project from winter through summer 2026, but the closure was still listed in mid-October and the page gives no new finish date. Parking Lot 1 has reduced capacity because of contractor staging, the restrooms are closed for emergency repairs, and portable toilets are in their place. The Carderock Pavilion and the towpath are open.
Between Cabin John and Seneca, the Great Falls Tavern area at milepost 14.3 is the main access point with no work-zone alert on the conditions page. The visitor center, parking lot, restrooms, Great Falls Overlook, Olmsted Island Boardwalk, Gold Mine Loop and River Trail are all open, as are Sections A, B and C of the Billy Goat Trail. The entrance road on MacArthur Boulevard is open. Flood-repair work there runs through 2026, so single-lane closures and short delays can still happen.
Canal boat rides at the tavern have ended for the season. Billy Goat Trail Section A depends on the river, not on construction. Under normal conditions it closes when the Little Falls gauge reaches 5 feet and reopens when the river drops to 4.8 feet. The visitor center at 301-739-4200 has same-day trail status during business hours.
The canal also changes each fall, separate from any project. The Park Service drains the watered sections every fall to protect the stone masonry from freezing, and water usually returns in early spring. As of October 14, the Widewater section and the stretch from Lock 17 to Lock 21 still held water, while the stretch from Lock 21 to Lock 23, which includes Pennyfield, was already drained.
The next several dates, in order:
These schedules cover only one part of a much larger program. DC Water describes a 10-year, $625 million rehabilitation of the Potomac Interceptor, and the Park Service reviews each proposed repair inside the park on its own ParkPlanning project page. One more of those projects is planned downriver near Little Falls. The Pennyfield and Lock 10 dates above are the current estimates for this winter, and Pennyfield's estimate has already slipped once.
Projects like these shape everyday routines along River Road and MacArthur Boulevard, and they can come up in conversations about where to live and how you will use the river. If you'd like to talk through how a particular stretch of the canal fits the way you want to live in Potomac, Catherine Triantis is glad to help. Let's Connect.
Stay up to date on the latest real estate trends.
Catherine Triantis carefully tailors her efforts to each individual's needs and preferences. Her success may be attributed to her consultative approach and commitment to consistent communication, attention to detail, and support through all phases of prep, strategic planning, and moving.